







Preview text:
  lOMoAR cPSD| 59054137 GRAVITY BASE  FOUNDATIONS        lOMoAR cPSD| 59054137       lOMoAR cPSD| 59054137  
Concrete gravity base foundations able to be 
floated and towed out to deeper water 
windfarms and installed without specialist 
marine equipment with minimum seabed  preparation.  CONTEXT   
The UK’s major programme towards sustainable, 
resilient, low carbon energy generation is pushing 
forward the next stages of offshore renewables. For the 
extensions to Round 2 and Round 3 in deeper waters a 
new reliable approach is needed for offshore wind 
turbine foundations. The Arup/Costain/Hochtief gravity 
base foundation provides this.      lOMoAR cPSD| 59054137  Turbine Foundation Selection 
 Optimum foundation selection is a function 
of the variables of water depth, turbine size 
and windfarm location conditions. As the 
water depth and turbine size increase, the 
applicability of steel monopiles becomes 
limited. This limit is further constrained by 
the harsher installation and operating 
conditions that prevail as the windfarm 
locations become progressively further 
offshore. The gravity base foundation 
provides an optimal solution for this 
broader range of operating conditions.   Gravity Base Foundations   Monopile Foundations      lOMoAR cPSD| 59054137 EXISTING FOUNDATION TYPES 
optimising installation flexibility and facilitating 
improved operation and maintenance. 
The current approach to turbine foundations 
typically has been steel monopiles. However, in 
The Arup/Costain/Hochtief gravity base responds, 
deeper waters and with larger turbines these reach 
following a research and development programme, as 
an upper limit which does not meet the 
a self-installing turbine foundation that can be mass 
requirements of the new windfarms, both in terms 
produced in construction facilities located in ports to 
of technical performance and offshore installation. 
suit rapid deployment to the UK windfarms. 
There is also a need to achieve greater flexibility 
through the supply chain that can increase the 
Concrete gravity bases can be successfully 
market’s capacity and avoid dependency on large 
deployed at all upcoming windfarms around the UK  scale steel tubulars. 
coast. For example, 84% of the Round 3 sites are 
in water depths over 30m, where concrete 
foundations may prove the best solution. Our 
gravity base foundation combines this with self-
installation to avoid the need for specialist and  expensive marine equipment.  < GRAVITY BASE   FOUNDATION    CONCRETE GRAVITY BASES 
Offshore windfarms are capital intensive projects 
and turbine foundations represent a quarter of 
their total delivery cost. The renewable industry 
is looking for creative yet dependable new 
approaches to drive down this cost, whilst      lOMoAR cPSD| 59054137
< Sweden’s largest offshore wind 
energy farm, Lillgrund, required  49 large concrete foundations  weighing around 1,400 tonnes  each. These were constructed  at a facility in Poland and  transported by sea to their 
required location. The concrete  foundations were placed very 
precisely onto their stone bases  located in water up to 11  metres.  KEY FEATURES & BENEFITS 
• Construction can be sited at ports well placed 
to suit windfarm locations, with discussions  Foundation Design  ongoing with selected ports 
• Reinforced concrete, non-piled, ballasted 
• Concrete costs are less dependent on  gravity structure 
commodities with high price volatility, such as 
• Caters for water depths up to 60m  steel 
• Suits larger turbine sizes up to an anticipated 
• Concrete gravity base foundations do not use  8MW 
large scale steel tubulars, therefore they will 
increase the market’s capacity to deliver 
• The design minimises the need for seabed 
preparation by accommodating existing 
turbine foundations, release supply chain 
seabed slopes and surface sediments 
constraints and increase competition 
• Construction can draw on existing resource 
• The design incorporates skirt variants to suit  seabed soil conditions 
pools close to the construction facilities 
• Existing supply chain capabilities can be 
• Designs can be standardised across 
< Safe working practices are 
implemented throughout projects 
from design to construction and  installation. 
> Building on existing experience of 
successfully installing a 600m long 
breakwater in the Pacific Ocean  that was made out of 12  slipformed 25,000t caisson 
structures fabricated in a purpose 
individual or multiple sites to enable cost 
leveraged to enable projects to start  optimisation  immediately 
• Collar design for the turbine mast connection 
• A dedicated mass construction facility will 
can accommodate ~2o vertical alignment 
deliver productivity benefits and reduce costs  tolerance 
• Health and safety considerations will be 
• Offers life cycle carbon footprint benefits 
integral to the development of the new  through material selection 
construction facilities and foundations 
constructed in them, using well proven safe 
• Unlike many alternatives, the design offers the 
potential to repower without foundation  construction expertise 
replacement Construction / Fabrication 
• The concrete bases are configured for rapid 
construction using readily available  construction skills 
• Construction is an onshore activity and 
tailored for ease of subsequent installation 
• Construction does not require deep water  (10m draft)    built dry dock.      lOMoAR cPSD| 59054137 Installation  Concrete volume  1,910m3 
• Foundations are self-buoyant for ease of 
deployment to the windfarm location  Steel reinforcement  720 tonne 
• Standard tugs that are readily available and  Partnership 
abundant are used to install the foundations 
The gravity base foundation is a development by a 
• Sea-borne noise and vibration is minimised so 
partnership between Hochtief, Costain and Arup, 
installation can progress year-round 
founded on long term relationships from previous 
projects and combines unique capabilities to serve 
• Reduced weather dependency 
significantly extends the installation season 
the growing energy sector. Hochtief’s strong  giving security of programme 
marine competence, Costain’s civil engineering 
and marine construction experience and Arup’s 
• Installation wil be achieved by sinking through 
offshore marine and concrete structure design 
the controlled influx of water, followed by 
expertise are the ideal basis to offer a unique and  sand/aggregate ballasting 
differentiated solution that ful y integrates the 
design, construction, offshore installation and  Operation 
decommissioning of foundations for offshore 
• Concrete has low maintenance requirements  windfarms. 
being inherently durable in the marine  environment 
• Scour protection wil be designed for minimum 
maintenance over the design life of the windfarm 
• The durability of the concrete gravity 
foundations could allow developers to re-deploy 
them in different locations with new turbines  fitted 
• Concrete gravity bases can be completely 
removed for recycling at the end of their useful  life Principal Data 
Key figures for 35m water depth, Central North 
Sea environmental conditions and 6MW can be  found below:  Air gap concrete structure  20m  Hub height above LAT  90m  Base outer diameter  34m  Outer diameter, caisson  31m  Outer diameter, top of shaft  6m      lOMoAR cPSD| 59054137 Contacts:  Gordon Jackson  Colin Duff  Fenno Leeuwerke  T +44 207 755 2289  T +44 1628 842444  T +49 40 21 986350 
E gordon.jackson@arup.com E colin.duff@costain.com E fenno.leeuwerke@hochtief.de 
For further information contact: (Back: Contact Title)  Name (Back: Contact Name) 
T xxxxxxxxxxxxxxxxxxx (Back: Numbers)  E 
xxxxxxxxxxxxxxxxxxxx ( Back: Numbers)    www.arup.com